Concrete slab calculator

Cubic metres and yards of ready-mix for a slab, with rebar grid, gravel base, vapour barrier and finishing labour.

Your job

Garage and basement floors are usually 4 in; driveways 4 to 6 in.

A grid of 10M bars in both directions at the chosen spacing.

0 for none. 3/4 in crushed stone, compacted.

Answer

Concrete to order
4.25 m³ (5.56 yd³)
Slab area
400 sq ft
Volume before waste
3.78 m³
Rebar
none
Gravel base
4.15 m³
Vapour barrier
440 sq ft
  • No reinforcing selected. Wire mesh or fibre may still be specified; check the drawings.

Method: Volume = length x width x thickness, plus waste; ordered in 0.25 m³ steps; Rebar: 10M bars both ways at the chosen spacing, 75 mm cover, 10% laps; 10M weighs 0.785 kg/m; Gravel base compacted allowance 10%; labour of 0.025 hours per sq ft is an estimating assumption

Estimating aid based on a summary of the CEC. Provinces adopt different editions and amendments. Confirm with the authority having jurisdiction, and the engineer of record where one is involved.

Priced takeoff

  • Ready-mix concrete 25 MPa, slab$858.504.25 m3 at $202.0014.88 h
  • Crushed gravel base, 3/4 in$246.724.15 m3 at $59.453.32 h
  • 6 mil polyethylene vapour barrier$39.60440 sqft at $0.093.52 h
  • Place, screed and finish slab (labour only)price pending400 sqft10 h
Materials
$1,144.82
Labour, 31.72 h at $105.00
$3,330.60
Your cost, before markup and tax
$4,475.42

Reference prices are dated baselines (2026-11) for Ontario. Confirm them with your supplier. In TradeQuote PRO your own saved prices replace these.

How it works

You enter 8 inputs. The calculator returns the quantities, rounds them up the way the material is sold, and lists the takeoff so it can be priced.

  • Length (ft).
  • Width (ft).
  • Thickness (in). Garage and basement floors are usually 4 in; driveways 4 to 6 in.
  • Waste allowance (%).
  • 10M rebar grid spacing. A grid of 10M bars in both directions at the chosen spacing.
  • Gravel base depth (in). 0 for none. 3/4 in crushed stone, compacted.
  • Vapour barrier under the slab. 6 mil polyethylene with 10% for laps.
  • Include placing and finishing labour. Turn off if your catalog concrete price already carries the labour.

The method

  • Volume = length x width x thickness, plus waste; ordered in 0.25 m³ steps
  • Rebar: 10M bars both ways at the chosen spacing, 75 mm cover, 10% laps; 10M weighs 0.785 kg/m
  • Gravel base compacted allowance 10%; labour of 0.025 hours per sq ft is an estimating assumption

Check results against the code and manufacturer data that apply to your job. Prices are dated baselines to confirm with a supplier.